    CONSTRUCTION OF NORTH AVENUE AND ADJACENT BUILDINGS WILL BE COMPLETED ON NOVEMBER 1, YERVAND ZAKHARIAN SAYS

    Noyan Tapan
    Sep 3, 2007

    YEREVAN, SEPTEMBER 3, NOYAN TAPAN. This year's construction work of
    Yerevan's North Avenue and adjacent buildings will be completed on
    November 1, the mayor of Yerevan Yervand Zakharian told reporters
    during his regular working visit to North Avenue on September 1. He
    said that on the whole he is satisfied with the speed and quality of
    construction, which are supervised 24 hours a day.

    According to the mayor, taking into account the large amount of work
    and shortage of time, working consultations will be held every week. A
    three-shift work schedule has been organized. A total of 600 builders
    have been involved in the construction work.

    To recap, construction of North Avenue's 500-meter-long residential
    section from Lalayants Street to Pushkin and Abovian Streets (with 15
    structures adjacent to the street) is at the final stage. Improvement
    work is currently being done in the Pushkin-Lalayants section.