    LINEUP WORK ON KAJARAN-ARARAT SECTION OF IRAN-ARMENIA GAS PIPELINE WILL FINISH IN AUTUMN

    Noyan Tapan
    March 31, 2008

    YEREVAN, MARCH 31, NOYAN TAPAN. It is envisaged to finish the lineup
    work on Kajaran-Jermuk-Ararat section of Iran-Armenia gas pipeline
    in the autumn of 2008. NT correspondent was informed from the press
    service of ArmRusgazprom that construction of Kajaran-Ararat section
    of the pipeline was disrupted in January because of the weather
    and resumed about a month ago. Construction work is being done in
    Kajaran-Sisian and Sisian-Jermuk-Ararat sections. The necessary number
    of pipes has already been brought to Armenia.

    The operation of 204.51-km Kajaran-Ararat gas pipeline will allow
    the increase the resource base of natural gas imported into Armenia
    via an alternative source.