    Azerbaijan : Kars-Akhalkalaki railway construction problems


    Construction of the Karsi-Akhalkalaki railway is proceeding very
    slowly. In 2009 it has stopped several times. Officially the first
    suspension was due to a very severe winter at the construction site,
    then a landslide at the place where the tunnel should have been built
    was blamed for another. Later some rumours appeared in the media that
    Russia was putting pressure on Azerbaijan to delay the project, but
    these have not been confirmed.

    Azerbaijan has allotted USD 200 million in credit to the project for
    25 years at a one percent interest rate. According to the Azeri media
    by the end of August 2009 only USD 33 million of this had actually
    been disbursed and the 100 million is planned for the end of this
    year. Georgian officials still express confidence that the part of the
    construction on Georgian territory will be completed by 2012.

    The Karsi-Akhalkalaki railway was fiercely opposed by Armenia, which
    suggested that the existing Karsi-Gumri (Armenia) tracks could be used
    instead as it needs only slight renovation. The normalising of
    Turkish-Armenian relations will eventually mean that this railway will
    be opened, but it is unlikely that cargo there could be transported to
    Azerbaijan until the Karabakh problem is settled. Therefore there is
    still a need for the Karsi-Akhalkalaki railway, and hopefully even
    with certain delays the project will be implemented.
    Ltd.

    From: Emil Lazarian | Ararat NewsPress