  • Construction Of Armenia-Georgia High-Voltage Electric Main Due To St

    CONSTRUCTION OF ARMENIA-GEORGIA HIGH-VOLTAGE ELECTRIC MAIN DUE TO START IN 2015

    YEREVAN, November 5. /ARKA/. Construction of 400 kVt electric main
    between Armenia and Georgia is planned to be started in 2015, Armenian
    deputy minister of energy and natural resources Ara Simonyan said at
    the draft budget discussions in the parliament commissions on Tuesday.

    A transition power line will be built in the first stage, and two
    existing mains will be connected to it.

    "This will enable us working with Georgia's energy system
    simultaneously", the deputy minister said.

    The second stage includes construction of the electric main from
    Hrazdan to Ayrum where the second module of the transition line will
    be built bringing exchange capacities between the countries from 200
    up to 700 megawatt, he said.

    The third part is linked to construction of the new nuclear power
    unit in Armenia and, hence, is due to start in 2026.

    Along with this, another 400 kVt power line construction project is
    implemented with Iran. Thus, Armenia will get involved in regional
    energy integration projects, the deputy minister said.

    According to the ministry's estimates, the total project cost is
    330 million euros, of it 300 million will be spent in the Armenian
    territory and the remaining part in Georgia. -0--