    PanARMENIAN.Net

    Kars-Akhalkalaki-Baku railway project likely to be signed in February
    26.01.2007 19:04 GMT+04:00

    /PanARMENIAN.Net/ The final intergovernmental agreement on
    construction of the Baku-Tbilisi-Akhalkalaki-Kars (BTAK) railway link
    is expected to be concluded in February. Azerbaijan Transport Ministry
    said the Presidents of Azerbaijan, Georgia and Turkey are scheduled to
    meet in Tbilisi to sign three documents - a framework agreement, terms
    agreement and loan agreement. The Ministry described the discussions
    held by the Azeri and Georgian delegations as fruitful. The parties
    agreed on the amount and procedure of the loan Azerbaijan is going to
    lend to Georgia for funding construction of Georgian part of the
    railway line. As per the agreement, Azerbaijan is going to extend a
    $200 mln unsecured loan to Georgia's Marabda-Kars Railroad LLC for 25
    years at 1% interest rate annually. The parties agreed that
    construction of Georgia parts of the project (98 km) will commence by
    July, 2007. The preliminary cost of the project is estimated at US
    $420 mln, reports APA.