Announcement

Collapse
No announcement yet.

Second Section Of Iran-Armenia Gas Pipeline To Be Built In 2008 - Ag

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • Second Section Of Iran-Armenia Gas Pipeline To Be Built In 2008 - Ag

    SECOND SECTION OF IRAN-ARMENIA GAS PIPELINE TO BE BUILT IN 2008 - AGENCY

    Arminfo
    30 May 07

    Yerevan, 30 May: HayRusgazard closed-type joint-stock company plans
    to invest 33bn drams (93m dollars) in the construction of the second
    section of the Iran-Armenia [gas] pipeline in 2007. In all, the company
    plans to invest 52bn drams (150m dollars) for the implementation of
    the project.

    The chairman of the board and CEO of HayRusgazard, Karen Karapetyan,
    has visited the construction area of the Kajaran-Ararat [section of
    the] pipeline together with experts.

    The press service of HayRusgazard reported that the construction of
    the 40 km Meghri-Kajaran section, as well as the 197.4 km section
    of the pipeline with a diameter of 720mm in the direction of
    Kajaran-Sisian-Jermuk-Ararat, will allow to raise the capacity of
    the system of gas transport. It will also provide the entry of the
    Iranian natural gas to Armenia in agreed volumes.

    [Passage omitted: technical and contractual details]

    Karapetyan said that the work on this section of the gas pipeline,
    stretching about 200 km, is planned to be done in 2007-08. In 2007,
    150 km of pipes will be bought, and 85 km of the pipeline will be
    constructed. He said that all the three shareholders of the company
    have the right to take part in the additional emission of shares with
    their proposals and partial participation.

    [Passage omitted: background details]