    THE PROBLEM WILL GET SOLUTION BY CONSTRUCTING A NEW WATER-PIPE
    by E. Davtian

    Azat Artsakh Tert, Nagorno Karabakh Republic
    Aug 29 2007

    The water-pipe netting of Hadrut was fitted in 1976. For water
    supply, at 3 km distance from the district centre 4 artesian wells
    were dug, pumping station was built, stationary strong pumps were
    mounted. For evading difficulties connected with exploitation
    of pumps "Parzaget-Hadrut" water-pipe of 5 km was built. In the
    years of Artsakh war either the pumping station or the artesian
    wells went out of order. The city began to get water only from the
    "Parzaget" water-pipe, which was not suited for drinking. With the
    help of "Hayastan" All-Armenian Fund in 1995 the second water-pipe
    "Parzaget-Hadrut" was placed. But the problem of drinking water was
    not solved again. The most probable version is the construction of
    "Ardjin aghbur" water-pipe, which is at 22 km distance from the
    district centres. By the program of "Rebirth of Artsakh" "Hayastan"
    All-Armenian Fund assigned the great part of the sums collected in 2006
    during the marathon to the construsction of "Ardjin aghbur-Hadrut"
    water-pipe. In announced competition "Viraj" was the winner, the
    head of which is V. Ataian. The building of the water-pipe has been
    foreseen to end in 2008, February. With all that, the builders of
    "Viraj" do everything to satisfy high level of the building and to
    put it into operation in time.